Skip to content
A plasterer spraying fire protection onto a steel column while a bricklayer measures the thickness of a brick wall, painted in late synthetic cubism

Code and compliance

NCC Fire-Resistant Building Elements: How an FRL Is Proved, the Deemed Thickness Tables for Walls, Columns and Beams, and What a House Needs (2025 Guide)

A wall, column, floor or beam is a fire-resistant building element when it holds a fire-resistance level, and NCC Volume Two Specification 1 sets the six ways to prove one: the deemed thickness tables, a tested prototype, an assessment of a near-identical element, a design to the structural standard, a calculation, or the fire-protected timber route. This guide walks through each with the clause, reproduces the deemed tables for masonry, concrete and gypsum walls and for protected steel, explains the Specification 2 detailing rules that come with them, shows where a house needs one, and includes a finder for steel column and beam protection.

The National Construction Code (NCC) never says "fire-resistant wall". It says a wall must have an FRL, a fire-resistance level, and then leaves a whole specification to explain how a wall, column, floor or beam proves it holds one. That specification is where the arguments happen on site: whether a brick wall "just is" fire-rated, how thick the concrete around a steel column has to be, and what piece of paper the certifier will accept. This guide reads Specification 1 of NCC 2025 Volume Two in order, with the clause beside each rule, reproduces the deemed thickness tables, explains the Specification 2 detailing that comes with them, and shows where a house needs a rated element in the first place. Our FRL guide covers what the three numbers mean and which FRL a Class 2 to 9 building needs; this one is about proving the element achieves it.

In one minute

  • A fire-resistant building element is one with an FRL: three periods in minutes for structural adequacy, integrity and insulation, determined under Specifications 1 and 2 (NCC glossary). Volume Two's A5G5 makes those two specifications the only way to determine one.

  • S1C2 gives six routes: the deemed thickness tables; a tested prototype; a near-identical element assessed by the laboratory; a design to the structural standard; a calculation from a tested prototype; or Specification 10 for fire-protected timber.

  • The deemed tables cover a narrow set of materials: ashlar, no-fines and plain concrete, gypsum blocks and plaster for walls, and concrete, gypsum, sprayed plaster or a masonry casing around hot-rolled steel columns and beams. Ordinary brick, blockwork and reinforced concrete are sent to AS 3700 and AS 3600 instead.

  • Every tabulated construction must also meet Specification 2: how masonry thickness is counted, the 20 and 27 height-to-thickness limits, filling the spaces round a column, and where the protection thickness is measured from.

  • A house needs a rated element in four places: an external wall within 900 mm of a boundary, a separating wall, a floor or projection over a neighbour's garage, and the walls of that garage. Each accepts 90 mm masonry in place of the 60/60/60 wall.

  • The figures are the same in NCC 2022 and NCC 2025.

1. What makes a building element fire-resistant

The glossary defines a fire-resistance level as the grading periods in minutes determined in accordance with Specifications 1 and 2 for structural adequacy, integrity and insulation, expressed in that order, with a dash meaning no requirement for that criterion. So 90/–/– asks only that the element stay standing for 90 minutes, and –/–/– asks nothing. The periods come from the Standard Fire Test, which the glossary defines as the fire-resistance tests of elements of building construction in AS 1530.4: a full-size prototype is loaded, sealed to a furnace and heated on a fixed curve while the laboratory watches for collapse, for flame or hot gas through a crack, and for the cool face reaching its temperature limit.

A5G5 of Volume Two then closes the loop: where a Deemed-to-Satisfy Provision requires a building element to have an FRL, it must be determined in accordance with Specifications 1 and 2. That sentence is the reason a brochure claim, a rule of thumb or a builder's assurance is not enough. The FRL is a defined quantity, and the specification defines how it is arrived at.

2. The six ways to prove an FRL (S1C2)

S1C2(1) says a building element meets the specification if it satisfies any one of six paragraphs. They are not ranked. The first is the cheapest where it applies, and the second and third are how almost every proprietary system reaches the market.

The element achieves its FRL if it…(a) is listed in Tables S1C2a to S1C2n and complies with themthe deemed thickness tables in this guide, read with Specification 2Evidence: the drawings(b) is identical to a prototype that passed the Standard Fire Test (AS 1530.4)an Accredited Testing Laboratory reports the test, the construction and the restraintEvidence: the test report (full or short-form)(c) differs only in a minor degree from that prototypethe laboratory certifies the FRL despite the departures and describes what must be keptEvidence: the assessment report(d) is designed to the fire section of the structural standardsteel AS/NZS 2327, AS 4100, AS/NZS 4600 · concrete AS 3600 · timber AS 1720.4 · masonry AS 3700Evidence: the engineer's certificate(e) has its FRL calculated from a tested prototype (S1C3)the report shows by calculation that the element would pass the testEvidence: the calculation report(f) is fire-protected timber complying with Specification 10the massive-timber route, where the fire-protective covering does the workEvidence: Specification 10 complianceAny one is enough (S1C2(1)). The FRL claimed under (b) or (c) is the one achieved without an active suppression system.
Clause S1C2(1): six independent ways an element can be shown to have its FRL, and the evidence each one produces for the certifier.

Three details in the clause matter in practice. The prototype in (b) must have achieved its FRL "without the assistance of an active fire suppression system", so a test run with sprinklers does not count. The report for (b) must describe the method, the conditions of test and the form of construction in full, and certify that the restraint applied to the prototype complied with the Standard Fire Test; restraint is the usual quiet difference between a good test result and a wall that behaves differently in a building. And (c) is the route most proprietary systems actually use: a manufacturer tests one wall and the laboratory assesses variations of it, so the assessment report must describe the materials, construction and conditions of restraint that are necessary to achieve the FRL. If the wall on site has a different lining, stud, insulation or fixing from the one described, the report no longer covers it.

3. The deemed thickness tables

Route (a) is a set of fourteen tables, S1C2a to S1C2n, each giving the minimum thickness of the principal material for five FRLs from 60 to 240 minutes. Every table ends with the same sentence: for the purposes of this table, each element must meet the requirements of Specification 2. The tables are older than most of the Code, and it shows in the materials they name. Ashlar stone, no-fines concrete, gypsum blocks and hollow terracotta blocks are all here; ordinary reinforced concrete, clay brick and concrete block are not tabulated at all but sent to their design standards.

Walls (Tables S1C2a, S1C2b and S1C2c)

Wall material60/60/6090/90/90120/120/120180/180/180240/240/240
Ashlar masonry300 mm
Calcium-silicate, concrete or fired-clay masonryDesign to AS 3700 (S1C2(d)(iv))
No-fines concrete150 mm300 mm
Plain (unreinforced) concrete150 mm170 mm
Reinforced or prestressed concreteDesign to AS 3600 (S1C2(d)(ii))
Solid gypsum blocks75 mm90 mm100 mm110 mm125 mm
Gypsum-perlite or gypsum-vermiculite plaster on metal lath and channel (non-loadbearing walls only)50 mm50 mm65 mm

Minimum thickness of the principal material. A dash is a combination the table does not deem to comply. The masonry and reinforced concrete rows cross-refer to the design standards rather than giving a figure.

The surprise for most readers is that brickwork has no row of its own. A 110 mm clay brick wall is rated by AS 3700's fire section, which sets the thickness for insulation and the slenderness for structural adequacy, not by a table in the Code. The Housing Provisions sidestep this for houses by accepting 90 mm masonry outright, which section 5 covers. Concrete columns, concrete beams and concrete floors, roofs and ceilings (Tables S1C2d, S1C2k and S1C2n) are the same: every row reads "see clause S1C2(d)(ii)", which is AS 3600.

Protected steel columns and beams (Tables S1C2e to S1C2m)

The steel tables are the ones people actually use. A hot-rolled steel column or beam, including a fabricated one, is deemed to achieve its FRL when wrapped in the listed thickness of concrete, gypsum, sprayed plaster or a masonry casing. The tables split by how many sides the fire can reach. A column exposed on no more than three sides, because it is built into or against a wall of solid masonry or concrete at least 100 mm thick (S2C19), is rated for all three criteria; a column or beam exposed on four sides is rated for structural adequacy only, so its columns read 60/–/– to 240/–/–. The masonry casings split again by whether the spaces between the casing and the steel are filled solid (S2C21): an unfilled casing stops at 120 minutes.

Cast or sprayed protection6090120180240
Column exposed on no more than 3 sides (Table S1C2e, FRL x/x/x)
Concrete cast in situ, loadbearing2530405575
Concrete cast in situ, non-loadbearing, unplastered2530405075
Concrete cast in situ, non-loadbearing, plastered 13 mm2525304050
Gypsum-perlite or gypsum-vermiculite plaster sprayed to contour2025355055
The same plaster sprayed on metal lath2020253545
Column exposed on 4 sides (Table S1C2h, FRL x/–/–)
Concrete cast in situ, loadbearing2540456590
Gypsum-perlite or gypsum-vermiculite plaster sprayed to contour2530405565
Beam exposed on no more than 3 sides (Table S1C2l, FRL x/–/–)
Concrete cast in situ2530405065
Gypsum-perlite or gypsum-vermiculite plaster sprayed to contour2025355055
Beam exposed on 4 sides (Table S1C2m, FRL x/–/–)
Concrete cast in situ2540456090
Gypsum-perlite or gypsum-vermiculite plaster sprayed to contour2030405565

Minimum thickness in millimetres. The full set, including the non-loadbearing and plaster-on-lath rows and the five masonry casings filled and unfilled, is in the finder below.

4. Find the protection thickness for a steel member

Choose the member, how many sides the fire reaches, the kind of protection and the FRL the element must achieve. The section draws the protection to scale and reads the thickness from the right table, with the Specification 2 rules that apply.

5. Where a house needs a fire-resistant element

Volume Two only calls for an FRL in a handful of places, and each one offers 90 mm masonry as an alternative to a rated wall, which is why the deemed tables are rarely opened for a Class 1 building. The four are in Part 9 of the Housing Provisions.

side boundary< 900123dwelling B, upper floor4garage of A(under B)garage of Bdwelling A1 External wall near a boundary: 9.2.3, 60/60/60 tested from outside, or 90 mm masonry veneer, or 90 mm masonry2 Separating wall: 9.3.1, 60/60/60 or 90 mm masonry, from the footings to the roof3 Floor over another dwelling's garage: 9.4.2, 30/30/30 tested from below, or a covering or 60-minute ceiling4 Wall to that garage: 9.4.1, 60/60/60 tested from the other garage, or 90 mm masonry
The four Housing Provisions that call for an FRL in a Class 1 building. Each wall rule accepts 90 mm masonry instead of a rated wall; the floor rule accepts a fire-protective covering or a 60-minute incipient-spread ceiling instead of 30/30/30.
  • External wall near a boundary. A wall required to be fire-resisting by 9.2.1 or 9.2.4, which our 900 mm boundary guide covers, must have an FRL of not less than 60/60/60 when tested from the outside, or be masonry-veneer with the veneer at least 90 mm thick, or be masonry at least 90 mm thick (9.2.3(2)). "Tested from the outside" is a Specification 1 point: the prototype must have faced the furnace on the side the fire would come from, because a stud wall lined differently on each face performs differently each way.

  • Separating wall. A wall between Class 1 buildings, or between a Class 1 building and a garage that is not its own, must have an FRL of not less than 60/60/60 or be masonry not less than 90 mm thick, start at the footings or slab and run to the underside of a non-combustible roof covering or 450 mm above a combustible one (9.3.1(1)). A lightweight separating wall must additionally be tested under Specification 6 (9.3.1(2)).

  • Horizontal projections and floors over a foreign garage. Where a floor forms part of the separation, 9.3.4 and 9.4.2 ask for 30/30/30 when tested from the underside, or a fire-protective covering on the underside of a combustible or metal floor, or a floor/ceiling system whose ceiling resists the incipient spread of fire for 60 minutes. Any part that the floor relies on for support must itself have 30/–/–.

  • Walls to a garage that belongs to another dwelling. 9.4.1 requires 60/60/60 tested from the other garage's side, or 90 mm masonry, from footings to the separating floor.

Read against Specification 1, the 90 mm masonry alternative is the Housing Provisions doing route (a)'s job by another means: the Code deems the wall adequate without an FRL being quoted at all. The moment a lightweight system is used instead, routes (b) and (c) apply and the wall lives or dies on its test or assessment report.

6. The Specification 2 rules that travel with the tables

Specification 2 exists only to describe the elements in Specification 1's tables (S2C1). Its clauses are short and each one has caught somebody.

manufacturing dimensioncores up to 25% of the volumeS2C10: a solid unitnet volume ÷ face areacores over 25% of the volumeS2C11 and S2C12: a hollow unitwall + one side's plasterplastered equally both sidesS2C14: ashlar, gypsum block, concreteHeight between lateral supports ÷ thickness must not exceed 20 (loadbearing) or 27 (non-loadbearing)for ashlar, no-fines, plain concrete, gypsum block and plaster-on-lath walls (S2C13).
Three of the counting rules in Specification 2. The thickness a table asks for is a calculated quantity, not the nominal size on the delivery docket.
  • Counting masonry thickness (S2C9 to S2C12). A unit with perforations or coring up to 25 per cent of its volume is solid, and the wall thickness is the manufacturing dimension of the units plus the specified joints. Over 25 per cent it is hollow, and the thickness is the unit's equivalent thickness, net volume divided by the area of one vertical face, plus the joints. A 190 mm hollow block with 40 per cent coring counts as a 114 mm wall.

  • Slenderness (S2C13). For ashlar, no-fines concrete, unreinforced concrete, solid gypsum blocks and plaster on metal lath and channel, the height between lateral supports divided by the overall thickness must not exceed 20 for a loadbearing wall or 27 for a non-loadbearing one. A 75 mm gypsum block partition is therefore limited to about 2 m between supports; add a head restraint or thicken it.

  • Plaster counts once (S2C14, S2C15). A wall of ashlar, gypsum block or concrete plastered on both sides to an equal thickness may add the thickness of one side's plaster to its table thickness. Columns have their own rule.

  • Column exposure and filling (S2C19, S2C21). A column built into, or in contact on one or more sides with, a wall of solid masonry or concrete at least 100 mm thick may be taken as exposed on no more than three sides. For a filled casing, the spaces between the fire-protective material and the steel, including re-entrant parts of the section, must be filled solid with concrete, gypsum or grout; the inside of a hollow section or pipe need not be.

  • Where the thickness is measured (S2C27). Protection to a steel column or beam is measured from the face or edge of the steel, from a splice plate, or from the outer part of a rivet or bolt, whichever is closest to the outside of the protection. Rivet heads may be ignored once the protection is 40 mm or more; at 50 mm or more an ordinary bolt may be ignored, a column splice plate within 900 mm of the floor may encroach by up to a quarter of the thickness, and on a member intended for 240 minutes a flange projecting 65 mm or more may encroach 12 mm. The rule does not apply to plaster sprayed to contour or on metal lath.

  • Reinforcing the protection (S2C23 to S2C26). A calcium-silicate, clay or concrete masonry casing needs steel-wire or mesh reinforcement in every second course, lapped at the corners; gypsum blocks and hollow terracotta blocks need it in every course. Structural concrete or poured gypsum is reinforced with wire mesh or binding about 20 mm from its outer surface, 3.15 mm wire at 100 mm vertical spacing, or 5 mm at 150 mm once the protection is 50 mm or more. Plaster sprayed to contour is reinforced with expanded metal lath or galvanised wire mesh where the surface exceeds the sizes in Tables S2C26a and S2C26b, set at least a third of the plaster thickness in from the face, and the plaster itself is mixed to the proportions in S2C5. The table thickness assumes all of this.

7. Calculated FRLs, interchangeable materials and two concessions

Calculation from a tested prototype (S1C3) is route (e). The element may vary from the prototype in length and height if it is a wall, height if it is a column, span if it is a floor, roof or beam, in its conditions of support, and to a minor degree in cross-section and components. The report must show by calculation that the element would achieve the FRL for structural adequacy including deflection, integrity and insulation, and must take into account the temperatures the components reached and their effect on strength and modulus, the support, restraint, slenderness, reinforcement and surface-area-to-mass features of the element, the features of the prototype and of the test conditions that influenced the result even if they were not part of the load design, and the design load compared with the prototype's. It is a fire engineer's document, not a manufacturer's letter.

Interchangeable materials (S1C4) lets a tested or tabulated concrete or plaster swap one Portland cement for another, one lime for another, one dense sand, one dense calcareous aggregate (limestone, calcareous gravel) or one dense siliceous aggregate (basalt, diorite, dolerite, granite, granodiorite, trachyte) for another in the same group and proportions, and treats gypsum-perlite and gypsum-vermiculite plaster as equivalent. A swap across groups, or a lightweight aggregate for a dense one, is not covered.

Columns covered with lightweight construction (S1C5): if the fire-resisting covering of a steel column is lightweight construction, a board system for instance, it must comply with Volume One C2D9 and C4D17 rather than the tables. Non-loadbearing elements (S1C6): where a non-loadbearing element is used in a place where the Deemed-to-Satisfy Provisions prescribe an FRL for all three criteria, it need not meet the structural adequacy criterion. A non-loadbearing partition asked for 60/60/60 only has to deliver –/60/60, which is why the test reports for such systems read that way.

8. The evidence the certifier can accept (A5G3)

Determining the FRL and documenting it are two steps. A5G5 governs the first; A5G3 lists the documentary evidence for the second, and its explanatory notes tie the two together. Where the FRL comes from a test under S1C2(b), the report from the Accredited Testing Laboratory may be either the full test report of clause 2.16.2 of AS 1530.4 or the regulatory information report of clause 2.16.3, the short-form report. Where it comes from an assessment under S1C2(c), the laboratory issues an assessment report certifying that the element achieves the FRL. In both cases the report must be unabridged: a page lifted from a brochure does not fulfil the description of "a report issued by an Accredited Testing Laboratory".

An Accredited Testing Laboratory is one accredited by NATA for the relevant tests, one accredited overseas by a body NATA recognises under a mutual recognition agreement, or one recognised as such under legislation when the test was done (glossary). Two other notes are worth keeping: documentary evidence that cites NCC 2019 clause numbers remains valid where the technical requirement is unchanged, so a 2019-era assessment report does not lapse because the clause is now S1C2; and the Standard Fire Test is one of the cases where the test itself must be done by an Accredited Testing Laboratory, even though A5G3 allows other forms of evidence to present the result.

9. Worked examples

SituationRouteResultWhere
House wall 600 mm from the side boundary, 110 mm clay brick veneerHousing Provisions alternativeComplies without an FRL: the veneer is at least 90 mm9.2.3(2)(b)
The same wall in timber frame and plasterboard(b) or (c)Needs a system with a test or assessment report of 60/60/60 tested from the outside9.2.3(2)(a); S1C2(b), (c); A5G3
Steel column in a 110 mm brick wall, 90/90/90 required, concrete encased(a)30 mm of loadbearing concrete cast in situ; exposed on 3 sides because the wall is at least 100 mmTable S1C2e; S2C19; S2C27
Free-standing steel column, 120/–/–, sprayed vermiculite to contour(a)40 mmTable S1C2h; S2C26
Steel beam under a concrete slab, 90/–/–, concrete encased(a)30 mmTable S1C2l
Steel column in a clay brick casing with the spaces unfilled, 180/–/– on 4 sides(a)Not deemed: the unfilled tables stop at 120. Fill the spaces (75 mm) or use another routeTables S1C2j and S1C2i; S2C21
Non-loadbearing gypsum block partition, 60/60/60 asked(a) with S1C675 mm blocks, height between supports not more than 27 × 75 = 2.0 m; structural adequacy not requiredTable S1C2c; S2C13; S1C6
Unreinforced concrete wall, 240/240/240(a)170 mm, or 150 mm for 180/180/180; plaster on both faces adds one side's thicknessTable S1C2b; S2C14
Reinforced concrete wall or column, any FRL(d)Design to the fire section of AS 3600; no table appliesS1C2(d)(ii)

10. Edition notes

Specification 1 and Specification 2 carry the same clauses, tables and values in NCC 2025 Volume Two as in NCC 2022, which introduced the S1C and S2C numbering; earlier editions held the same tables under different labels, which is why A5G3 preserves evidence written against NCC 2019 references. New South Wales, Queensland and South Australia stay on NCC 2022 until 1 May 2027, and the Northern Territory has not adopted NCC 2025; the figures above are the same either way. Volume One's Specification 1 carries the same routes and the same tables for Class 2 to 9 buildings.

When you next have a certifier ask how a wall "is" fire-rated, the answer is one of the six paragraphs of S1C2, the table or report that goes with it, and the Specification 2 detail that makes the table apply. AEC Assistant can find the clause, the table row and the state variation for the element in front of you, with the source cited, and read the test report you upload against the wall on the drawings.

Questions this guide answers

What is a fire-resistant building element in the NCC?

A building element that has a fire-resistance level (FRL): the grading periods in minutes for structural adequacy, integrity and insulation, determined in accordance with Specifications 1 and 2 of the NCC. A wall, floor, column, beam or roof becomes a fire-resistant element when a Deemed-to-Satisfy Provision asks it to carry an FRL and it is proved to hold one.

How is an FRL determined under the NCC?

Clause S1C2 of Specification 1 gives six routes: the element is listed in the deemed thickness tables S1C2a to S1C2n; it is identical to a prototype that passed the Standard Fire Test in AS 1530.4 and an Accredited Testing Laboratory reported the result; it differs only in a minor degree from that prototype and the laboratory has certified the FRL; it is designed to the fire section of AS/NZS 2327, AS 4100 and AS/NZS 4600 (steel), AS 3600 (concrete), AS 1720.4 (timber) or AS 3700 (masonry); it is calculated from a tested prototype under S1C3; or, for fire-protected timber, it complies with Specification 10.

How thick does a wall need to be for FRL 60/60/60?

The deemed tables give 75 mm for solid gypsum blocks and 50 mm for gypsum-perlite or gypsum-vermiculite plaster on metal lath and channel (non-loadbearing only). Clay, concrete and calcium-silicate masonry, and reinforced or prestressed concrete, are not tabulated for 60/60/60: they are designed to AS 3700 or AS 3600 under S1C2(d). For a house, Housing Provisions 9.2.3 and 9.3.1 accept 90 mm masonry in place of the 60/60/60 wall without any table.

How much concrete does a steel column need for a 120 minute FRL?

For a hot-rolled steel column exposed on no more than three sides, 40 mm of loadbearing concrete cast in situ gives 120/120/120 (Table S1C2e); exposed on all four sides it needs 45 mm for 120/–/– (Table S1C2h). Sprayed gypsum-perlite or gypsum-vermiculite plaster to contour needs 35 mm and 40 mm respectively. The thickness is measured from the nearest face of the steel, splice plate or bolt under S2C27.

What evidence do I need to show an element has its FRL?

A5G5 says the FRL must be determined under Specifications 1 and 2, and A5G3 lists the acceptable documentary evidence. For a tested element that is the full test report or the short-form regulatory information report from an Accredited Testing Laboratory under AS 1530.4; for a near-identical element it is the laboratory's assessment report certifying the FRL. Reports must be unabridged. Evidence written against NCC 2019 clause numbers stays valid where the technical requirement is unchanged.

Did NCC 2025 change the fire-resistance specification?

No. Specification 1 and its tables carry the same values in NCC 2025 Volume Two as in NCC 2022, which introduced the S1C numbering. New South Wales, Queensland and South Australia stay on NCC 2022 until 1 May 2027, and the figures are the same either way.

Ask it the question you were about to look up

Free for NCC 2025 and NCC 2022 with citations, and planning information for any address in Australia. No credit card.